The Exceptions list
This list type shows exceptions made per work center. If there are saved exceptions from basic time or from number of machines for a work center, it will be shown in the list. This list type does not show information about work centers of the type Pool and Subcontract. It is not possible to update any information in this list.
If the system setting Enable hourly planning for work center is activated, then there are two presentations of this list type:
- Day planning
Day planning is used when you are NOT applying hourly planning. It means that all operations are planned to a date and not to a specific time on a date. – Here you see the work centers which have saved exceptions from basic time, of the work centers with the time precision Day planning.
- Schedules – In this presentation you see the work centers which have a saved schedule exception, of the work centers with the time precision Capacity via schedule or Hourly planning
Hourly planning refers to when planning per work center is done per hour. Hourly planning is activated with a system setting. Period is then entered as date and time. You can view loading on hour basis..