Lead time to printing list

The list is loaded and displayed based on the selection and settings you have chosen. As in all lists in Monitor ERP, you can drag and drop in order to change the column to group by.

This list shows how many days have passed between purchase order registration and the order being sent to the supplier.

Example of calculating lead time to printing

Order date_ 2024-05-15 (a Wednesday)

Print date: 2024-05-21 (a Tuesday)

Calendar Wed. 15 Thur. 16 Fri. 17 Sat. 18 Sun. 19 Mon. 20 Tues. 21
Standard calendar 0 1 2 Not a work day Not a work day 3 Lead timeClosed Number of days between ordering date and delivery date. Normally used for purchased parts. to printing 4 days
All calendar days 0 1 2 3 4 5 Lead time to printing 6 days

If you are using the standard calendar, your country’s holidays will not be included in the calculation.