Phases/Activities

Under this tab, the phases and activities of the project is shown. You can for example see information regarding who is responsible for the activity, reported hours, when the activity is planned to start, and when it is planned to finish. At the bottom of the tab you see totals of planned time, reported time, and remaining time.

You can expand a phase using the button to the left of the phase number. In the expanded mode you can see the activities belonging to the phase. You can use the button Expand all on the function menu (Shift + F8) to expand all of the phases at once.

With the button Show lead time chart you can open the lead time chart in a separate floating window. Read more about the lead time chart.

If you in a quick and easy way want to report time/cost for an activity in the activity list in the project, then you can use the button and link/go to the procedure Direct project reporting with the record you have marked already loaded. You can also double-click on the row.

Add activities/phases

By using the regular function buttons you can add, insert, and delete rows for activities/phases.

With the button Add activity template you can add an activity template at the bottom of the list. With the button Insert activity template you can insert an activity template above the row you are on in the list. When you use these functions a dialog will open where you enter which template to use and the start and end date. Activity templates are handled in the procedure Basic dataClosed With "basic data" we refer to the static records in a database, for example parts, customers, users, work centers, etc. – Project.

Change template

It is possible to change activity template with the button next to the field Activity template on the header row. It is possible to change template if the project is saved, as long as nothing has been reported on the activity. When something has been reported on an activity, it is no longer possible to change template.

When you change template for a project, the start and end times of the activities should be calculated using the start date of the project as a basis. And also using the queue time, lead time, and project responsible from the template. Start date is automatically set according to the project's start date and using the template the end date is calculated. However, it is possible to change the end date and then the start date will be recalculated. The calculated start and end date will be the project's new date under the Main.

Remember choosing start and end date according to the start and end time of the project. When adding/inserting activity templates, today's date is by default used as start date.

Generate activities via template in new project

If you have registered templates (in the procedure Basic data – Project) for the project type in question, then these will be generated when you create a new project. The activities will then get start and end date automatically calculated by using the start and end date of the project + the lead time and queue time which you entered in the template. The person responsible for the activity and the phases are also entered according to the template.

Change start and end date for the project

In the topic Project time you can read about start date and end date and how the dates of the activities will be affected by changes made.

Phases and Activities

For new phases and activities added separately (that is, added outside a template), information for the activity/phase is loaded according to the settings in Basic Data – Project. If the phases and activities are taken from a template when creating a new project they will get values according to the template.

For an activity list it is not mandatory to have a phase. It is possible to only have activities in a project.